Student Flow & Sequence Architect
Calculated CPA: 15 mins
Design Your Transformation Sequence & Task Times
Use the π Draw / Toggle Sequence Arrow tool on the canvas above (click a start station, then click a destination station) OR toggle the sequence links below to see how parallel vs. sequential flows change the Critical Path and Gantt schedule!
B: Grill Patty8m
C: Toast Bun4m
D: Fry Chips6m
π Active Sequence Connections (Click any chip to remove, or use canvas π tool to add):
β
Sequence Audit: All stations are connected in a valid parallel network!
π₯ Active Critical Path (Longest Sequence):
A (2m) → B (8m) → E (3m) → G (2m) = 15m
π‘ Why Parallel Scheduling Matters:
Running B, C, and D in parallel saves 12 minutes per order compared to a single-file serial line!
Live Auto-Generated Gantt Chart
Scale: 0m β 30mWatch the Gantt bars shift horizontally in real time as you re-wire station dependencies! Red bars are on the Critical Path; blue bars have Slack Time.
π Try This Experiment: Click "π’ Single-Line Serial Flow (27m)" above the canvas. Notice how chaining
A → B → C → D → E → F → G forces every station to wait in line, nearly doubling your Gantt chart from 15m to 27m!